Completed Projects

NRW-Water Supply Project South Part Of Colombo City

Colombo

NRW-Water Supply Project South Part Of Colombo City

Client – National water supply & drainage board - NWS&DB
Project Cost - 14 Million LKR
Main Contractor – Savinda Enterprises

Here is the we are acting as sub subcontractor for pipe laying works.  Our scop consists of 10 Km HDPE pipe laying, Culvert crossings, manhole construction with related works. Value of total work done over 10 million LKR. Total project period – 1 year (2022-2023)

Kandy Waste Water Management Projects

Kandy

Kandy Waste Water Management Projects

Client – National Water Supply & Drainage Board - NWS&DB
Main Contractor - Kolon Global Corporation

Here is the we are subcontractor for pipe laying works.  Our Scope consists of 10 km UPVC pipe laying, I C chamber placing, manhole construction with related works. Value of our part nearly 40 million. Project period 1 year.

NRW – Water Project (East Of Colombo City)

Colombo

NRW – Water Project (East Of Colombo City)

Client – National Water Supply & Drainage Board (Nwsdb)
Main Contractor - Kolon Global Corporation

Here is the we are acting as Main subcontractor for pipe laying works.  Our scop consists of 40 Km HDPE pipe laying, Culvert crossings, manhole construction with related works. Value of total work done over 280 million LKR. Total project completed whiten 3 years (2017-2020)

Water Project (West Of Colombo City)

Colombo

Water Project (West Of Colombo City)

Client – National Water Supply & Drainage Board
Main Contractor - Chaina Harbor & Chaina-Geo JV.

Here also we are act as subcontractor for pipe laying works.  Our scop consists of 10 Km HDPE pipe laying, Culvert crossings, manhole construction with related works. Value of total work done over 30 million LKR. Total project period – 1 year (2021-2022)

Matara Stage-IV Water Supply Project

Matara

Matara Stage-IV Water Supply Project

Client – National Water Supply & Drainage Board (Nwsdb)
Main Contractor - Kolon Global Corporation

Here is the we are subcontractor for pipe laying works for main transmission line.  Our scop consists of 6 Km Dia. 560 mm HDPE pipe laying, Culvert crossings, manhole construction with related works. Value of total work done over 15 million LKR. Total project period – 6 month (2021-2022)

Stelinberg Mini Hydro Power Project

Nuwareliya

Stelinberg Mini Hydro Power Project

Client – Lotus Energy PLC

Here is the we are acting as main contractor weir, pipe line and outlet area construction. Value of total work done over 15 million LKR. Total project period – 6 month (2016-2017)

NRW – Water Project (North Of Colombo City)

Colombo

NRW – Water Project (North Of Colombo City)

Client – National Water Supply & Drainage Board (NWSDB) Main Contractor - Toda – Sierra Jv
Project Cost - 15 Million

House Construction At Walapane (Design & Build)

Walapane

House Construction At Walapane (Design & Build)

Client – Mrs. D K Sandamali
Project Cost - 30 Million

: Here is the contractor. Our scope is build 3 story home, finishing with related works. Value of total work done over 25 million LKR. Total project period – 6 month (2017-2020)

Karapalagma Mini Hydro Power Project

Karapalagma

Karapalagma Mini Hydro Power Project

Client – Sierra Power (Pvt) LTD
Main Contractor: South Asia Economic Development and Construction Corporation

Here is the we are acting as sub-contractor. our scope is construction Part of Headdress Channel and project infrastructure construction. Value of total work done over 05 million LKR. Total project period – 6 month (2014)

Ranmudu-oya Mini Hydro Power Project

Ranmudu Oya

Ranmudu-oya Mini Hydro Power Project

Client – Laugs Power PLC
Main Contractor - Sentab International (Pvt) Ltd

Description: Here is the we are acting as sub-contractor, our scope is construction power House. Value of total work done over 8 million LKR. Total project period – 6 month (2014)

Trust and Worth